Timeline

Find out more about the past, and future, timeline of events.

Developer Requirements

The Development Consent Order (DCO) approved in May 2020 included 20 requirements the Developer must satisfy before development works can commence. The outline details of these are: Time limits – the development must commence no later then 28 May 2025 Detailed design approval – no phase of the development may commence until all aspects of…

DECISION MADE: Application granted consent

The Secretary of State for Business, Energy and Industrial Strategy granted development consent for the Project. For further information please refer to the following documents: Secretary of State Decision Letter Development Consent Order as Made Examining Authority’s Recommendation Report Planning Inspectorate Decision Cover Letter Habitats Regulations Assessment Regulation 31 Notice

1 2 4